Monday, January 30, 2012

WFES: Fund launched to accelerate solar in East Africa

25 January 2012

Eight19 Ltd., the developer of the IndiGo pay-as-you-go solar power system and SunnyMoney, a social enterprise distributing solar lamps in East Africa owned by SolarAid, have launched the KickStart Sustainable Energy Fund for off-grid solar lighting in East Africa.

By Kari Williamson
The fund, which was launched at the World Future Energy Summit (WFES) last week, is part of an ongoing partnership aimed at expanding affordable solar lighting to rural off-grid communities in East Africa. The initial investment will fund the deployment of 4000 IndiGo units.
KickStart will provide working capital to accelerate the roll-out of IndiGo pay-as-you-go solar lighting products in rural off-grid communities. Users receive solar lighting and in-home phone charging, which they pay for on a weekly basis using scratchcards, just like a pay-as-you-go mobile phone.
The revenues from the scratchcards recover the cost of the solar units and are returned to KickStart to allow the deployment of additional units to new users.
The programme has been primed with a pool from Eight19 and SolarAid of US$200,000 to cover the first 4000 lighting systems to be deployed in Kenya in early 2012.
Steve Andrews, CEO of SolarAid, says: “1.6 billion people - over one fifth of the world’s population - lack access to the electricity grid and pay high prices for kerosene to serve basic needs such as lighting. IndiGo technology provides an affordable means of delivering electricity using the sun’s power to generate clean, renewable energy at the point of use. The KickStart Fund, which is administered by SunnyMoney’s owner, the registered charity SolarAid, will provide working capital to enable IndiGo-enabled solar lights to be help many more families, bringing enormous economic benefits to local communities across the developing world.”
Simon Bransfield Garth, CEO of Eight19, adds: “The IndiGo system makes electricity affordable because it allows users to buy electricity as a service, avoiding the expensive upfront costs normally associated with solar products. Since we launched IndiGo in September 2011, the technology has been met with great enthusiasm and the KickStart fund will further accelerate the deployment of solar power and all the benefits it brings.”

IndiGo solar units

Eight19, launched its IndiGo pay-as-you-go personal solar electricity system for off-grid communities in Kenya in September 2011.
Users purchase scratchcards at approximately US$1 per week for a standard system, which represents less than half the typical cost of the kerosene lighting and phone charging spend it displaces.
Each IndiGo system consists of a low-cost solar panel, a battery unit with inbuilt mobile phone charger and a high efficiency light emitting diode (LED) lamp.

This article is featured in: Solar electricity

Namibia: Energy Needs Outweigh Environment Concerns

Flag of Namibia.svg

NAMPOWER'S envisioned coal-fired power station at Arandis will present a unique case where the social and environmental impact of such a project on a small town of about 6 000 people will have to be weighed against the government's obligation to guarantee a critical basic need of over two million Namibians.
This was an observation at a public meeting at Arandis on Saturday during which the findings of draft scoping report for an 800MW coal-fired power station were presented.
The report will be submitted to the Ministry of Environment and Tourism's Department for Environmental Affairs for approval, so that the Social and Environmental Impact Assessment process can continue.
Namibia's bulk power utility hopes its new power station will start producing electricity by 2015 - even if it is at an initial capacity of 150MW to 300MW. At least this, combined with the Ruacana, Van Eck and Anixas power plants, could make up for Namibia's peak energy demand of over 500MW - and growing.
Electricity Control Board (ECB) chief executive officer Siseho Simasiku said during last year's electricity supply stakeholders' forum in Walvis Bay that Namibia's energy issue has become a "critical national security matter", which was bigger than socio-economic concerns.
This concern was emphasised at Saturday's meeting. Electricity provision from neighbouring countries are being scaled down drastically because there is a general shortage of power supply in the southern African region as a whole.
Added to this is Namibia's increasing domestic and industrial appetite for electricity - from a country where power plant infrastructure is either old, small or dependent on external factors for optimal operation such as the Ruacana hydropower plant, which depends on a strong water flow.
The latest addition to the national power grid was the N$350 million 22,5 MegaWatt (MW) 'Anixas' diesel power station at Walvis Bay, commissioned last year; the first bulk electricity generator to be inaugurated since the Ruacana hydropower station that was opened in 1978. Anixas is a crucial link in the electricity grid, but will not be Namibia's saviour when it comes to bulk supply.
Nampower's current installed generation capacity is 415,5MW, with a peak demand of 511MW recorded in June last year, which excludes the 96MW requirement of the Skorpion Zinc mine in the south.
In addition, it is estimated that the growth in energy demand for this year will be 4,4 per cent with a corresponding growth in demand requirement of 4,6 per cent, according to a background information document of NamPower related to the proposed coal power station.
The shortfall to date was supplemented through energy imports over Namibia's interconnected transmission network with the Southern African Power Pool countries. During some periods the energy imports can be as high as 80 per cent of energy requirements.
This reliance on imported energy poses a big risk for Namibia though, as the region not only experiences power shortages but the transmission networks in neighbouring countries are congested.
Projects in the region are suffering from delays and in some cases are not being implemented at all.
The energy white paper of Namibia states objectives for more secure and reliable energy. It highlights that Namibia should aim to supply all of its demand (MW) and at least 75 per cent of its energy (MW per hour) requirements from its own installed generation capacity.
The proposed coal power station is one of the potential solutions to the current situation, and a site about six kilometres east of Arandis seems to have caught Nampower's eye.
Environmentally speaking, out of all the possible sites, which included sites near Walvis Bay and Swakopmund, as well as west of Arandis, the eastern location would seem to have the least impact.
Another element that played an important role in NamPower opting for the site is the town council's readiness to make land available for the initiative.
The Arandis town council is working exhaustively in turning this little town into the industrial hub of the region.
It even held its first investment conference during the last quarter of 2011 for which it has received much acclaim and support, according to the town's mayor, Daniel Muhuura.
The untimely availability of land for a seriously critical energy generator was what eventually led to plans for the erection of the coal-fired power station in Walvis Bay falling flat.
In general, considering the "modern and proven, but not experimental" technology to be used that will reduce pollutants by more than 90 per cent; the availability of coal, and the possibility of utilising biofuels and other organics; and limited impact on the environment, there is not really anything than can stop the plant from materialising east of Arandis.
Generally speaking, when it comes to large projects that have specialised markets, the social impact may very well outweigh the desire for the project, but the proposed coal-fired power station, like any other national infrastructure development, is an exception to the rule when it comes to the consideration of impacts.

Nairobi, Addis in landmark 400MW power purchase deal

Details of the high-stakes negotiations before Kenya signed a 400MW electricity deal with Ethiopia two weeks ago are emerging, revealing that Nairobi managed to talk down the initial charges proposed by Addis Ababa as too high.

Details of the high-stakes negotiations before Kenya signed a 400MW electricity deal with Ethiopia two weeks ago are emerging, revealing that Nairobi managed to talk down the initial charges proposed by Addis Ababa as too high. 
By KENNEDY SENELWA  (email the author

Posted  Sunday, January 22  2012 at  15:34
Details of the high-stakes negotiations before Kenya signed a 400MW electricity deal with Ethiopia two weeks ago are emerging, revealing that Nairobi managed to talk down the initial charges proposed by Addis Ababa as too high.
The deal, which analysts say presages a new era of power trading in the region, was arrived at after a great deal of haggling, with the Ethiopians pressing for a higher price on the grounds that Kenya is currently buying even more expensive power from thermal plants.
The deal ushers in one of the biggest power pool projects in the region, and will serve as a model for future arrangements under the Eastern Africa Power Pool.
The deal is a take or pay contract, meaning that Kenya has to pay for the 400 MW supply even if it is not using it.
It will pay US cents 7 per kilowatt hour. The transmission line is expected to be completed by 2016 at a total cost of $1.2 billion.
The agreement for continuous supply of 400MW was concluded in Addis Ababa by Kenya Power and the Ethiopian Electric Power Corporation after two days of intense negotiations from January 6-8.
The power purchase agreement is the second in Kenya’s history as it seeks long term solutions to its perennial power problems. A decade ago, Kenya imported about 30MW from Uganda.
The conclusion of the agreement paves the way for Kenya and Ethiopia to mobilise funds for building a 1,045-kilometre high voltage electricity transmission line. Ethiopia, which is endowed with a huge hydropower potential of about 45,000 MW, is currently building three dams to generate power for domestic use and export to Kenya and other neighbouring countries.
Other projects under the Power Pool are under way, with the goal being to create a regional electricity network.
Tanzania will be connected to its neighbours through the planned Kenya-Tanzania interconnection and through the extension of the Tanzania grid to the northwestern Rusumo Falls Hydropower Project shared among Burundi, Rwanda and Tanzania. Meanwhile, Uganda and DR Congo are planning to extend the Ugandan electricity network to Beni and Bunia in DR Congo through a transmission line, Nkenda-Beni-Bunia.
According to the Kenya Electricity Transmission Company (Ketraco), Agence Française de Développement (AFD) of France, the African Development Bank and the World Bank have expressed a commitment to funding the Kenya-Ethiopia project.
Ketraco was a few years ago hived off from Kenya Power to exclusively build infrastructure for high voltage transmission. Kenya Power as a distributor is in charge of smaller voltage lines for connecting end-users.
Ethiopia is the only country in the region with surplus power, backed up by by a reserve margin of more than 30 per cent, double the recommended margin of 15 per cent. “Donors like the French are keen to support the transmission line project.
Kenya’s funding is about $666 million and Ethiopia’s $486 million,” said Ketraco managing director Joel Kiilu. He said selection of consultants to oversee building of the transmission line, designed with power transfer capacity of 2,000MW, will start soon and construction work begins in mid-2013 with a completion date of 2016.
The high voltage direct current (HVDC) line requires putting up of steel towers, transmission cables and inverter substations at Suswa in Kenya and Welayta Sodo in Ethiopia. The HVDC line will start from Welayta Sodo and run south along Lakes Abaya and Chamo, through Konso and cross the Kenyan border about 90 kilometres west of Moyale town.
From Moyale, the transmission line will run through Marsabit, Samburu, Laikipia, Nyandarua and Nakuru counties to terminate at Suswa. Kenya and Ethiopia have formed a joint project co-ordination unit (JPCU). Ketraco is finalising bid documents and tenders are to be floated in April.
The surplus electricity applicable at any time will be agreed on by the parties three months before commencement of supply, taking into account economies of scale and other relevant factors. Completion of the high voltage electricity line is expected to open avenues for big consumers such as cement manufacturers to enter into negations for supply of cheap power directly with Ethiopia.
Mr Kiilu said Ketraco is working on other interconnection facilities like the Lessos-Toro line with Uganda and Isinya-Arusha line with Tanzania to address power shortages and unreliability of supply in the region. The implementation of the Lessos-Tororo line is at an advanced stage as the project has attracted the required financing.  
Courtesy of East African

Uganda: Power crisis weighs down economy

THURSDAY, 19 JANUARY 2012 01:27 WRITTEN BY MOSES TALEMWA



When Parliament’s ad hoc committee probing the energy sector reconvened this week after the Christmas recess, chairman and West Budama South MP Jacob Oboth indicated that they had a tight agenda ahead of them.
The committee plans to meet key government officials and to conclude its report in two weeks. According to Oboth, this report is expected to set the tempo by which the power sector will run, beginning this year. The committee is set to meet key sector ministers, Irene Muloni, Simon D’Ujanga and Hilary Onek, as well as minister of State for Finance Aston Kajara and long-serving permanent secretary Fred Kabagambe Kaliisa. The five are expected to explain the various discrepancies in the sector that led to a crisis, which now makes doing business in Uganda the most expensive in the region.
“We need to get to the bottom of this crisis so that when our report comes out, it is so comprehensive that our groundbreaking resolutions will not be ignored,” Oboth says. The MP has met several groups of players who were involved in the evolution of the sector from 2004, when Umeme first took over from the disbanded Uganda Electricity Board.
Many in the business community are also watching the committee closely to see if its final report will mirror their own findings and concerns.
“We have been doing our own research and we intend to publish our report on January 20 before we call for decisive action,” Issa Sekitto, Kampala City Traders Association spokesperson reveals.
Sekitto says KACITA is convinced the electricity crisis is unsustainable and unnecessary as Uganda is now the most expensive in the region. “As you know most (businesses) start out small and are eventually knocked out by high electricity tariffs or the lack of power,” Sekitto says.
However, Sekitto’s comments couldn’t have come at a worse time. The Electricity Regulatory Authority (ERA) recently issued new tariffs, following government’s decision to withdraw the subsidy on the cost of electricity. The decision effectively increases the cost of power by 70% (from Shs 184.8 to Shs 312 for the large consumers and 38% for the medium scale consumers from Shs 333.2 to Shs 458.9).
Uganda Manufacturers Association members, who are already incensed by the move with some calling for a strike, want a public hearing on the matter as it affects their survival.
“UMA demands an urgent fair hearing by government on this matter that fundamentally affects the present and future members of UMA over and above having far-reaching social economic consequences for Uganda as a whole,” UMA chairman Kaddu Kiberu demanded in a letter on Monday.
At around the same time, the Oboth committee summoned the Electricity Regulatory Authority (ERA) and demanded that it withdraw the new rates, after realizing that, contrary to regular practice, the ERA board had not sat to decide on them.
“We demand that you withdraw these rates or else we shall send the people onto the streets to demonstrate against you,” Kasilo county MP Elijah Okupa said.
ERA executive director Benon Mugisha Mutambi said it was unsustainable to keep the power tariffs at the old rate. Once outside the house, the director for Energy and Mineral Development in the  ministry, Paul Mubiru, weighed in on the matter: “The concerns of the ad hoc committee have been noted but the reality is that the process has already taken place. It is difficult for the committee to change the tariff back because the mandate for this lies with ERA.
The committee can only make recommendations to Parliament which would then discuss them and change them if a resolution is made. But the Electricity Act is clear and makes no provision for tariffs to be taken to Parliament for endorsement.”
Mutambi later added that unlike in the past, ERA would review the tariff once every month from April going forward and the cost of power would not be going down.
“So far there is nothing to show that once Bujagali comes on stream, the cost of power will come down. So, it is unrealistic to expect lower power tariffs,” Mutambi said.
In explaining this, Mutambi says the current power deficit is 172MW, which they hope will be resolved when Bujagali is fully commissioned. But then he expects population growth to have translated into higher demand for power.
Sekitto says the trading community is already fed up and will not hesitate to take action.
“The electricity tariff is unnecessarily high and this must end. We are ready to take to the streets to ensure that our demands are met.,” the KACITA spokesperson said.

Contractual Issues

The ad hoc committee is also already concerned about the contract that brought Umeme into Uganda’s power sector.
“The negotiating team knows very little about the [concession] agreement than those who are now investigating it, and worse still they don’t even recognize that it’s a bad deal that makes the tax payer a prisoner,” Oboth said late last year.
The Auditor General has also raised queries about Umeme’s losses and the level of investment onto the national grid. Under the contract, Umeme is entitled to claim compensation from the government for any losses incurred while conducting business, but the Auditor General doesn’t believe the loss levels are genuine. His appearance before the committee in the coming days will shed light on this.

Power Generation

So far, the committee has discovered that there are serious problems in how power is generated at Jinja. While meeting the director of Water Resources (DWR), Mugisha Shillingi, the parliamentary committee discovered that the country is ill-equipped to monitor the water that goes into the two dams Kiira and Nalubaale to generate power.
“We do not have any staff in Jinja; we only monitor the water that is discharged into the dam by looking at the gauges after Eskom has released the water. To my understanding Eskom uses the water we allow them to use,” Shillingi told the committee.
However, he admitted that the DWR was unable to independently ascertain whether Eskom was following instructions. He explained that from a technical perspective the dams, including the yet-to-be-connected Bujagali hydro power plant are designed to handle 800 cubic metres of water per second. However, the President recently directed Shillingi to increase the water discharge rate to 1,000 cubic metres per second to enable more reliance on hydro power than the more expensive thermal power.
On the thorny issue of whether Bujagali can produce 250MW, Shillingi, said the new plant was designed with a flow of 800 cubic metres per second, and could generate 250MW of power for up to six hours a day, which is when that kind of electricity is usually needed.

mtalemwa@observer.ug

Turkana project to create 2,800 jobs

SATURDAY, 21 JANUARY 2012 00:15 BY JAMES MBUGUA
A massive wind power project in Lake Turkana region will create 2800 jobs over the next 3 years mainly in construction. Carlo Van Wageningen, the chairman of Lake Turkana Power, the consortium that is undertaking the project, yesterday said the 300Megawatt project will see the installation of 365 wind turbines over 40,000 acres.
It will be the largest wind project in the world when completed. “We have to build a village to accommodate all the staff,” Wageningen said at a press briefing in Nairobi. Other projects include the construction of a road that the consortium will undertake, installation of a 105kilometre interconnection between the wind turbines and deployment of static synchronous condensers to stabilize the system.
Wageningen said concurrent construction of a transmission line from the area to Suswa would be carried out by the Kenya Electricity Transmission Company (Ketraco). The wind farm project will cost 583million euros (Sh64billion) while the transmission line will cost 142million euros (Sh15.6billion) for a total of Sh80billion at current exchange rates. “We expect to be online at the end of the last quarter (December) 2013 with 50MW with completion in the last quarter of 2014,” Wageningen said.
He said 70 per cent of the project funding will come from commercial lenders with 30 per cent coming from cash injection by shareholders. “Our lenders are completing the stages to get financial close,” the chairman added. Shareholders include Aldwych which own Rabai power plant (25 per cent), IDC of South Africa (25 per cent), Norfund and Vestas (25 per cent each), Danish IFU (6.25 per cent ) and KPMP (8.75 per cent). Wageningen said Kenya has very good wind with potential for up to 15,000MW in the Lake Turkana/Marsabit region. “This will be the highest load power capacity in the world,” he said.


Courtesy of The Star

Ethiopia planning to carryout feasibility studies on three additional hydropower plants

  JANUARY 30, 2012

"Asfaw Dingamo and Tom Odegaard"
The Mandaya and Beko Abo Dams are situated in the Blue Nile Sub-basin and among the top high dams in the world, respectively having a 200 mts and 285 mts height, an installed capacity of 2000 MW and 2100 MW and an annual energy output of 12,119 GWh/year and 12,600 GWh/year.
Senior ministers at the Ministry of Water & Energy (MoWE) are planning to carryout feasibility studies on three additional hydropower plants to be built in the basin of the Abay (Blue Nile) River, whose combined power generation capacity is projected to be larger than the Grand Renaissance Dam, Fortune learnt.
The cost of the feasibility studies on the technical, environmental, and social impacts of the dams will be covered with a 20.1 million-dollar grant secured from the government of Norway.
Asfaw Dingamo, former minister of Water Resources, had signed the grant agreement with Tom Odegaard, in November 2009.
Hydroelectric power plants planned in Mendaia, Beko Abo, and Kara Dodi, will collectively have 300MW more power than the Grand Renaissance Dam’s 5,200MW, a capacity the dam is believed to have when the Italian Salini Construttori completes construction in the second quarter of 2017. It will be the largest hydropower plant on the continent, with 15 generating units, each producing 350MW of electric power, a capacity currently generated by Koka and Tekeze dams combined.
The Grand Renaissance Dam also symbolises the nation’s determination to build the largest dam ever with its own resources, according to Prime Minister Meles Zenawi.
“The other dams we plan to build are less challenging than this,” he had said during his address at the launching of the project in Guba, Benishangul Gumuz Regional State, on April 2, 2011.
Indeed, he was referring to hydropower projects on the drawing board such as Beko Abo (2,100MW), located two kilometres upstream of Nekemt Bridge; Mendaia (2,000MW), located seven kilometres upstream on the Abay River and Dedessa River confluence; and Kara Dodi (1,600MW), located 70km upstream from the Renaissance Bridge.
However, the actual generation capacity of each dam will have to be determined after the feasibility studies are complete.
“Their capacities might increase or otherwise,” a hydraulic expert at the Ministry told Fortune.
Mendaia and Beko Abo projects are expected to be roller compacted concrete (RCC) dams, with 200 metre and 285 metre heights, making the latter the highest of its type in the world, each having an annual energy output of over 12,000 GWh a year.
The prefeasibility studies on Mendaia and Bako Abo projects were conducted by a consortium of consultants from Norway (Norplan and Norconsult), France (Electricite de France), and England (Scott Wilson), as well as Shebelle Consult Plc and Tropics Consulting Engineers, both domestic firms.
The report for the studies was approved by the Ministry after reviewing reports from the consultants, following consultation with the Ethiopian Electric Power Cooperation (EEPCo) and other relevant stake holders, sources disclosed.
The prefeasibility study includes hydrology studies, topography surveys, and geotechnical foundation and environmental studies. Aside from hydropower generation, the projects also aim to be multipurpose, providing improvements in flood control and conservation.
“The Ministry approved the projects, confirming their economic and technical viability, as eligible for a final feasibility study,” a senior official at the Ministry told Fortune.
Studies on economic and social viability were carried out by foreign consultant: Halcrow and Generation Integrated Rural Development (GIRD). It was during these studies that a helicopter crashed in the Abay Gorge, after it collided with a cable en route from Gojam to Wellega; no harm was reported.
The aforementioned consortium has been given the job of conducting the feasibility studies. They are allowed to take about six months to complete them, according to the senior official at the Ministry.
“If all of the studies are finalised within the year, as planned, construction will start within the coming few years,” he disclosed to Fortune.
The cost of building all three dams is yet to be determined. Nonetheless, it may reach close to 75 billion Br, considering the 13 million Br average cost per megawatt that the five most recent dams, including the Grand Renaissance Dam, have consumed in the past or are projected to.
“By the time we secure financing for their construction, these projects will be ready to be carried out within the five-year transformation period,” said the senior official at the Ministry.
The Ministry is also commissioning economic feasibility studies on the Tekeze River, for its second dam, 903km north of Addis Abeba, and on the Dedessa River, in Benishangul Gumuz, 386km from the capital. The two projects will have an estimated capacity of producing 450MW and 301MW, respectively.
The successful construction of these dams will increase the nation’s hydroelectric power plants to 17.
Currently, EEPCo generates 2,000MW of power, while an additional 8,000MW is expected in the coming three years; of which 97MW has already been added after Fincha Amertinesh Dam, consuming 137.8 million dollars, was inaugurated last month.
source: addis fortune

Friday, January 27, 2012

Zimbabwe Power Demand to Rise 29% in 2012, Supply Authority Says

Zimbabwe Flag By Godfrey Marawanyika
Jan. 3 (Bloomberg) -- Zimbabwe’s electricity demand is projected to increase 29 percent this year, boosted by the mining industry, the state power utility said.
Demand rose 6.2 percent last year from 2010, Fullard Gwasira, a spokesman for the Zimbabwe Electricity Supply Authority, said by phone today from the capital, Harare.
Zesa generates 900 megawatts to 1,200 megawatts compared with demand of 1,900 to 2,200 megawatts. The country imports 35 percent of its electricity from Mozambique and Democratic Republic of Congo, yet fails to meet demand, resulting in almost daily power cuts. Zimbabwe is the third-largest power consumer in sub-Saharan Africa after South Africa and Nigeria, according to the World Bank.
The country’s economy is estimated to expand 9.4 percent in 2012, led by growth in the finance and mining industries, Finance Minister Tendai Biti said on Nov. 24. The economy was forecast to grow 9.3 percent in 2011, with mining output climbing 26 percent as the nation attempts to recover from a decade-long recession that ended in 2009, Biti said.
Zimbabwe Electricity Transmission and Distribution, a unit of Zesa, said power demand by mines in the nation’s northern region is expected to advance 22 percent in 2012.
“Developments in the mining sector include Maranatha Ferrochrome at 13 megavolt amperes, Mazoe gold mine at 5.5 megavolt amperes and RioZim Ltd. at 5 megavolt amperes,” Harare-based ZETDC said in a report handed to Bloomberg News.
Industry, Agriculture Demand
Maranatha is a closely held company. Mazoe is owned by South Africa’s Metallon Corp. while RioZim was once controlled by Rio Tinto Plc.
Demand by the industrial sector is forecast to rise 55 percent while farms will raise demand by 33 percent, ZETDC said.
In the nation’s southern region, the Mimosa mine, owned by Aquarius Platinum Ltd. and Impala Platinum Ltd., plans to start using 15 megavolt amperes, while the Wel mine, owned by Chinese investors, will need 5 megavolt amperes, ZETDC said. Sino- Zimbabwe Ltd. of China is planning an additional 6 megavolt amperes.
--With assistance from Brian Latham in Johannesburg. Editors: Ana Monteiro, Randall Hackley
To contact the reporter on this story: Godfrey Marawanyika in Johannesburg at gmarawanyika@bloomberg.net

China completes cross-border power transmission project with Russia

BEIJING, Jan. 1 (Xinhua) -- State Grid Corporation of China (SGCC), the country's largest power supplier, said Sunday it has put to trial operation a cross-border electricity transmission project in northeastern Heilongjiang province to supply Chinese with Russia's electric power exports.
The electric power SGCC purchased from Russia began reaching Chinese customers late Saturday night after the completion of the direct-current back-to-back networking substation, or called "the trans-Amur project" by Russians, SGCC said in a statement on its website.
The trial operation will last 168 hours, SGCC said in the statement.
With a transmission capacity of 750 mega-watts, the electricity transmission project is China's biggest cross-border power line, according to SGCC.
"The implementation of the project will gain experience for the expansion of Sino-Russian energy cooperation and help promote the economic development for both countries," SGCC said.
The project is also part of the Sino-Russian energy and trade cooperation.
Russian Deputy Energy Minister Andrei Shishkin said in June 2011 that the transmission project would increase Russia's power supply to five or six billion kilowatt hours of electricity to China and Russia intended to increase its electricity supply to China in the coming years.
Russian companies plan export 60 billion kwh of electricity to China by 2020. Power plants will be built along its border with China to reduce power transmission losses and reduce transportation costs.
Also on Sunday, an oil pipeline linking Russia's far east and northeast China witnessed its one year anniversary of operation, as operators announced an accumulated 15 million tonnes of oil had been transported into China in 2011.

Editor:Zhang Pengfei |Source: Xinhua